Composite Flooring

Floor clip system

Why use this system?

The hidden clip system allows WPC composite planks to be installed without visible screws on the surface.

The clips are inserted into the side groove of the slat and fixed to the batten, ensuring a firm, uniform and aesthetically clean hold.

Before Installing

Surface

  1. The base should be firm, stable, and perfectly level.

  2. The battens should be placed 300–350 mm apart and fixed with screws every 500 mm.

  3. It is mandatory to leave a minimum separation of 15 mm between the structure and any wall or fixed obstacle to allow the expansion of the material.

  4. Proper ventilation under the platform must be ensured to prevent moisture build-up and ensure the durability of the system.

  5. A slight slope outwards is recommended to facilitate water evacuation.

Material

  1. The slats should be installed exclusively with the recommended clips and screws, with no visible fixings on the surface.

  2. It is advisable to pre-drill before screwing to ensure precise fixing and avoid damage to the material.

  3. The clip system automatically maintains the proper separation between slats, allowing their natural expansion.

  4. The ends of each slat must always rest on a batten to ensure stability and structural strength.

Surface map

What does the system include?

T_CLIP

T-Clip (PP)

Intermediate fastening element that joins slat and batten invisibly.

START/END CLIPS

Start/End Clips

Allows to fix the first and last slats.

Specific screws

Specific screws

Guarantees firm and durable support.

Finishing

Side trim (Optional)

Finishing profile for a professional aesthetic finish.

Invisible installation without surface screws

Invisible installation without surface screws

Allows natural longitudinal expansion

Allows natural longitudinal expansion

High outdoor resistance

High resistance outdoors

Fast

Fast and efficient system

Clean and professional finish

Clean and professional finish

Steps to install with
PP T-Clip system

STEP 1 COMPOSITE FLOORING

STEP 1

Installation of the batten

Fixing of the base structure ensuring leveling and correct separation.

STEP 2

Install the initial clip

Placement of the starter clip at the end to position the first slat.

STEP 2 COMPOSITE FLOORING
STEP 3a COMPOSITE FLOORING

STEP 3

T-Clip Fitting (PP)

Insertion of the T-Clip into the side slot and attachment to the batten.

STEP 4

Installing the slat

Slat fitting over the T-Clip, ensuring alignment and separation.

STEP 4 COMPOSITE FLOORING
5

STEP 5

Continue installation

Repetition of the process while maintaining a uniform installation.

STEP 6

Install the side finial

Side profile placement for a clean finish

6