The wall must be firm, flat, and completely level before installing the substructure.
It is mandatory to install a batten substructure, without directly fixing the panels to the wall.
Battens must be placed with a maximum spacing of 500 mm to ensure structural stability.
In horizontal installation, the spacing between screws should be maintained approximately every 400 mm.
Proper ventilation between the wall and the cladding must be ensured to prevent moisture build-up and improve the durability of the system